Projects

Baloži

Construction of connecting pipe section to join two independent heating networks.

About the project

  • Client SIA «Baložu siltums»
  • Construction by SIA «UPB energy»
  • Investment 1,3 million EUR
  • Project co-financed by EU structural funds

Technical specification

  • New pipe system length 3 km
  • 5914 meters of FiberFlex pre-insulated, flexible thermoplastic pipes
  • Pipe size DN 140 mm
  • Pipe system max working temperature Tmax= 95 0C
  • Pipe system max working pressure Pmax= 10 bar