Projects
Valdemārpils
Merging two independent heating districts in one centralized system.
About the project
- Client SIA «Talsu namsaimnieks»
- Construction by SIA «Grobiņas SPMK»
- Investment 0,35 million EUR
- Project co-financed by EU structural funds.
Technical specification
- New pipe system length 980 m
- 1960 meters of FiberFlex pre-insulated, flexible thermoplastic pipes
- Pipe size range DN 40 up to DN 125 mm
- Pipe system max working temperature Tmax= 95 0C
- Pipe system max working pressure Pmax= 10 bar
Construction finished July 2020.